《配电施工流程.pdf》由会员分享,可在线阅读,更多相关《配电施工流程.pdf(8页珍藏版)》请在三个皮匠报告上搜索。
1、Distribution Construction ProcessDistribution Construction ProcessZachary Southworth,Project ManagerPresented by Carrine Mullin,Manager Distributed Energy ResourcesCentral Hudson Distributed Energy ResourcesKey Project MilestonesKey Project Milestones25%PAYMENT75%PAYMENTMECHANICAL COMPLETIONPROJECT
2、INTERCONNECTIONEngineering,Procurement,Construction25%Payment25%Payment Schedule Site Visit At the site visit,team will review pole layout,POI configuration,easements,license agreements,and current project documentation Project Schedule Utility to provide developer with preliminary project schedule
3、Utility Design Review Developer to submit any site plan modifications Estimating team begins the design for the project and identifies any necessary easements/permits that might be required75%Payment75%Payment Site Visit with Utility Stake poles and anchors(once access road installed)Utility to prov
4、ide final project schedule Easement(s)/Permits(s)Central Hudson will prepare any necessary easements/license agreements for the project and obtain any necessary permits Developer will complete the easements with property owner and submit original to PM Complete Project Design Utility to finalize the
5、 design Procure project materials and equipment Schedule utility construction with operationsMechanical Completion/Post ConstructionMechanical Completion/Post Construction New Account CreationDeveloper to complete new commercial account applicationProvide the Underwriter permit for meter pan(cut in
6、card)EnergizationSubmit the electrical inspection for the DG systemUtility to set meter and program the recloserSelf Verification Test Recommended for developer to have a relay technician on site during this test Final Witness TestOnce a su