1、ZESCO Solar PV ProjectsPresenter:Francis NamakandaDate:27November 2025Thisinformation hasbeen classified ZESCO ConfidentialExternal.Project Objectives/Benefits:Increased Electricity Generation and Availability:Reliable power supply forZambia.Economic Growth:Enhanced productivity for farming,fishing,

2、and localbusinesses.Access to Affordable Green Energy:Reduced reliance on biomass and dieselgenerators.Reduced Carbon Emissions:Contribution to climate change mitigation.Lower Energy Costs:Reduced cost of energy generation compared to fossil fuels.Alignment with SDGs:SDG 7:Affordable and Clean Energ

3、y SDG 12:Responsible Consumption and Production SDG 13:Climate Action1.1 ScopeThe scope of the phase II project involves the establishment of a 100MW solar plant adjacent to theexisting 100MW Chisamba Phase I Solar plant.The contract was fully executed on 2 September 2025.The Project cost is US$76.8

4、M1.2 Status of the ProjectSite cleared 100%,compaction and levelling at 100%progress.Equipment foundation civil works in progress.Detailed engineering design in progress1.4 Project SummaryCOD is July 20261.100MW Chisamba Phase II4100MW Chisamba Phase II-Control Room Foundations2.1 ScopeThe project i

5、nvolves establishment of 100MWac solar plant Chipata nearest to Chipata West 330/132/33kV Substation.COD is June 2026.2.2 Status of the ProjectContract fully signedSite handover done on 19 September 2025.Site Clearing commenced and at 50%progress.Detailed engineering design in progress2.3 Project Su

6、mmaryCOD is expected to be June 20262.100MW Chipata West6100MW Chipata West-Site Clearing and leveling3.1 ScopeThe project involves establishment of 50MWac solar plant in Mansa District of Luapula Province.The project isexpected to cost US$48M.The Project is being developed by ZESCO Limited.3.2 Stat

word格式文档无特别注明外均可编辑修改,预览文件经过压缩,下载原文更清晰!
三个皮匠报告文库所有资源均是客户上传分享,仅供网友学习交流,未经上传用户书面授权,请勿作商用。
1. **项目目标**:增加电力供应、促进经济增长、提供平价绿色能源、减少碳排放及降低能源成本, align with SDG 7、12、13。 2. **主要项目**: - **Chisamba Phase II**:100MW太阳能电站,毗邻一期,成本7680万美元,2026年7月投运,场地清理完成。 - **Chipata West**:100MW电站,靠近330/132/33kV变电站,2026年6月投运,场地清理50%。 - **Mansa**:50MW电站,成本4800万美元,2025年底投运,进度80%。 3. **其他项目**:包括Mumbwa(50MW)、Mailo II(35MW)、Kasupe系列(15MW)、Siavonga(100MW)等,2025-2026年陆续投运。 4. **储能项目**:Chadiza、Monze等7个BESS项目(2.5-5MW),2025-2026年投运,合同签署中。
**项目进展如何?** **成本效益怎样?** **何时完工?**
客服
商务合作
小程序
服务号
折叠