1、Eli Lilly Comes to ConcordIntroductions Alex Burris Began career with City of Concord Electric in 2000.Held many positions within the department and was promoted to Director in 2019.Caleb Greene Started at the City of Concord in 2013 Promoted to Special Projects Manager in 2023 Managed the 2nd half

2、of the Eli Lilly project in ConcordEli Lilly Facts Currently a 1.05 Trillion Dollar Company,who has a workforce of about 47,000 employees worldwide Eli Lilly and Company is a major American multinational pharmaceutical corporation,founded in 1876 by Colonel Eli Lilly in Indianapolis,known for develo

3、ping high-quality medicines,pioneering insulin production,and becoming a global leader in healthcare through innovation,especially in areas like diabetes and obesity treatments.History of This Property in Cabarrus County A 2000-acre parcel right in the middle of Concord and Cabarrus County Was owned

4、 and used by Philip-Morris from 1982-2009 and was the largest tobacco processing and distribution facility in the world.Was on the market for sale for 6 years until a private investor group purchased it.PM Property Sold to Investment Groups Philip Morris was fed by Duke(City had no footprint on the

5、property)Building was demod in 2017 and property was subdivided Entire campus was in City limits,so at that time,the City gained service rights to this property(2000 acres).Electric Dept began planning and prep for how were going to serve this property.Prep to serve property Reached out to Duke in 2

6、017 about adding a 100kV delivery 2 new retail 12kV substations in the area 100kV transmission line extensions to complete two 100kV loopsEli Lilly Comes to Town Lilly started talking to County and City management about possibly locating here in 2021-2022 City,County&Electric Eco

word格式文档无特别注明外均可编辑修改,预览文件经过压缩,下载原文更清晰!
三个皮匠报告文库所有资源均是客户上传分享,仅供网友学习交流,未经上传用户书面授权,请勿作商用。
1. **项目背景**:康科德市为吸引礼来公司(Eli Lilly,市值1.05万亿美元,全球员工4.7万),在其原菲利普·莫里斯烟草厂(2000亩)建设供电设施。 2. **核心需求**:礼来初始要求8MW负载、电力冗余、太阳能阵列,最终升级为专属变电站,双100kV供电回路,2025年Q1投运。 3. **建设成果**:康科德电力部门耗时701天(提前6个月),成本低于预估7%,建成含双变压器、6台断路器的变电站。 4. **挑战与应对**:克服供应链中断、成本上涨、环保问题等,夜间/节假日施工保障进度。 5. **太阳能规划**:初步规划10-15MW太阳能,变电站预留太阳能断路器,2025年12月提交5MW申请。 6. **经验总结**:关注工业用地、电网容量不足区域,与经济部门紧密合作。
**Eli Lilly为何选址?** **项目如何提前完工?** **太阳能计划如何?**
客服
商务合作
小程序
服务号
折叠