1、 Disclosures&Disclaimer This report must be read with the disclosures and the analyst certifications in the Disclosure appendix,and with the Disclaimer,which forms part of it.Issuer of report:HSBC Qianhai Securities Limited View HSBC Qianhai Securities at:https:/ Capacity is being ramped up at sever

2、al large projects and their operational status is key to watch Besides technological advancement,we see changes in grid policies that could benefit green hydrogen projects Prefer Sungrow Power(rated Buy);maintain Buy on CNCEC(lower TP to RMB12.33 from RMB12.80)and Hold on Longi Project plan and exec

3、ution have picked up in 2025 YTD.In 1H25,a total of 2726 MW electrolysers were tendered,more than the total tendering of 2239 MW in the full-year 2024.This is an uptick from the slowdown in 2024.While actual electrolyser deliveries might be less than the orders(as occurred in 2022-24),several mega p

4、rojects are going into operation this year,marking true progress.In July 2025,the first phases of three mega projects entered trial operations:the Chifeng(green ammonia),Daan(green ammonia)and Taonan(green methanol)projects.These projects have announced overseas clients uptake contracts and have sho

5、wn technological progress.For example,the Chifeng project is running off-grid and relying on 100%solar/wind energy(as per Sina Finance,16 July 2025).We believe more time is needed to verify the projects operational status and the scale of their long-term overseas selling contracts.If these projects

6、operate smoothly,the green hydrogen business could be fully commercialised once the economics improve.We have seen operational progress at Sinopecs Kuga project,as its average utilisation was 32.5%in the past two years,and it is expected to reach full utilisation in 2026.Still many bright spots.We h

word格式文档无特别注明外均可编辑修改,预览文件经过压缩,下载原文更清晰!
三个皮匠报告文库所有资源均是客户上传分享,仅供网友学习交流,未经上传用户书面授权,请勿作商用。
根据《Data》标记内容,以下是全文关键点概括: 1. 中国绿色氢能项目执行和电解槽招标在2025年上半年加速,电解槽招标量达到2726兆瓦,超过2024年全年2239兆瓦的招标总量。 2. 2025年,中国绿色氢能行业进入关键时期,需要验证大型项目是否能顺利运营,以及是否存在重大技术障碍。 3. 中国政府推出了一系列新的电网政策,可能有利于绿色氢能项目,如可再生能源直接接入政策和现货交易政策。 4. 全球氨价格疲软,但中国绿色氨项目可能通过大规模和长期交易实现突破。 5. 钢铁制造领域应用氢能取得进展,中国钢铁研究总院集团开始建设使用绿色氢的钢铁厂。 6. 长期来看,电解槽市场增长潜力大,Longi和Sungrow Power等公司有望受益。 7. 中国绿色氢能行业与全球市场相比,面临许多项目延误和取消,但一些国有企业领先私营企业决心推进试点项目和开始运营。
"绿氢项目加速,投资机会在哪?" "电解槽市场风云,谁将脱颖而出?" "绿色氢能,未来可期!"
客服
商务合作
小程序
服务号
折叠